打拆阶段
项目地址:天河区尚河居
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/526c9d6db17942148a161b09a2e7b0e5_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/bec0f96364ab49bda1e6141d1bbca48a_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
我们会在施工前,往运输材料的通道铺上保护膜,以免造成磨损,给业主带来不便。
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/5a13932c90954e1d97b6d541862ed1d5_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/a16c90f4fb56400585cd40b4b99a1f86_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
房屋打拆时我们不仅会铲除墙、地面的所有装修设施,还会拆除户型改造的墙体,使其成为一个毛坯房的状态。
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/c0dc9bd0990a431bb7cd8471e5e3924e_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/3123c47e89bc4f1c9059eaba487f2f30_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
打拆完后师傅将装修垃圾都及时清理出去了,以方便后续的施工能更加顺利进行。
砌墙阶段
项目地址:白云区同泰路
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/2134899a69a94e22914ac325a7cdd745_w300X399_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/c147b8c7d88e43c18ae1b24dd277a0cd_w300X399_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
为了巩固新砌的墙体和旧墙的稳定性,我们会植入钢筋,减少墙体之间开裂的风险。
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/4683c3e34f904e7b8e08c29c42a0f7bf_w300X399_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/74282dd0969d4388af43d29e087d9894_w300X399_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
门洞口会先用钢筋和水泥预制门梁,避免后期门洞受力变形,压迫门变形或者打不开。
水电阶段
项目地址:越秀区永泰西约
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/7f713603fa8f4206a3a095a0c9053288_w300X225_w196X147.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
水电布局一如既往地整齐美观,横平竖直的线路不仅利于线管的保护,还给后期的施工提供了许多便利。
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/a96eff520a9143fb9681b03b3483acd2_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/063b1d37a0ca4322be5645b467a3b71a_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
电线管在拐弯时我们会使用大弧弯处理方式,这样既不容易损坏电线,也方便日后的抽线维修。
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/75686ebb89474ccb82be66deb5e91767_w300X225_w196X147.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
走墙的电线管我们会事先在墙上开槽,再进行预埋,保证墙面的平整度。
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/2dc4acc45a334af7a6f32379b7983372_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
强弱电线交叉时需要使用锡箔纸包裹,水电交叉时则遵循电路在上、水路在下的安装原则。
防水阶段
项目地址:天河区尚河居
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/7900dbf97da4467f90f2acafd55a469f_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/30a9b68ae47142709d288e042098f4a9_w300X399_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
在涂刷防水层前我们会先对墙地面进行找平,再使用刚性和柔性结合的防水材料涂刷,使防水效果实现最佳化。
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/ba1ddf1b090042a995cb47b9ddfdb5d0_w300X225_w196X147.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
待防水涂层刷好并干透后,就可以蓄水进行闭水试验,观察48小时以上,没发现渗漏问题则说明防水工程合格。
![](https://qimg.cdnmama.com/gz/data/attachment/forum/2024/05/06/cf0d6362f59f49698e32df4c1bbd1738_w300X400_w196X261.jpeg?imageView2/2/w/600/h/0/format/jpg/q/90)
闭水试验完后,需要将水排出并清理干净,然后才能进行下一道工序。
了解工期进展,把控工地质量,是我们一直在巡检的工作目的,让每一个家都能实现高质量落地。